​​​​​​Project Classification Breakdown

   
Project Stages Stage 0 Strategic Definition Stage 1 Prep and Brief Stage 2 Concept Design Stage 3 Spatial Coordination Stage 4 Technical Design Stage 5 Manufacturing and Construction Stage 6 Handover
H&S Teams input Attend meetings and give guidance  Attend meetings and give guidance  Review and give guidance Review and give guidance Review and give guidance Review and give guidance Review and give guidance
Others Client & Design Team  Client & Design Team  Client & Design Team  Client & Design Team  Client & Design Team & Project Director/Manager & CoW Client & Design Team & Project Director/Manager & CoW Client & Design Team & Project Director/Manager & CoW
Type A No H&S Involvement (Stage 0-4) Asset Information Asset Information Issued
Type B1 Initial Bid Review Design Risk Register Design Risk Register No H&S Involvement (Stage 4-6)
    Pre-Construction Information aid PD with compiling
Type B2 Initial Bid Review Tender Reviews Pre-Construction Information No H&S Involvement (Stage 5-6)
ITT and tender review Design Risk Register  Design Risk Register must mitigate any hazards and ensure controls are in place where there is a residual risk.
   
Type B3 Project Manager role to ensure they are suitable. If CoW role only, this does not apply.
Type C No H&S Involvement (Stage 0-3) Construction Health and Safety Plan Asset Information

Safe System of Works

Lite Site Inspections
Asset Information Issued
Ensure Pre-construction Information has been issued and is adequate  
2 Days 3 Hours 1 Hour
Type D1 Initial Specification Gather Pre-Construction Information from the Client/Landlord     Construction Health and Safety Plan Asset Information

Safe System of Works

Lite Site Inspections
Asset Information Issued
  Design Risk Register  Ensure Pre-Construction Information has been issued.If not adiquate FCDOS will need to carry out additional surveys
    Design Risk Register must mitigate any hazards and ensure controls are in place where there is a residual risk.
Type D2 Initial Bid Review Tender Reviews     Construction Phase Plan Produce Safe System of Works
Method Statements, Permit to Works.

 Carry out Construction Site Inspection reports
(Weekly/Monthly) conducted by CoW
Health and Safety File Issued
ITT and tender review Gather Pre-Construction Information  Pre-Construction Information
  Design Risk Register  Design Risk Register must mitigate any hazards and ensure controls are in place where there is a residual risk. Feed back information to the Principal Contactor if alterations to the Construction Phase Plan are required *Only when there is a fundamental change to the scope of works
    Health and Safety file.
Project Stages Stage 0 Strategic Definition Stage 1 Prep and Brief Stage 2 Concept Design Stage 3 Spatial Coordination Stage 4 Technical Design Stage 5 Manufacturing and Construction Stage 6 Handover
Others Client & Design Team  Client & Design Team  Client & Design Team  Client & Design Team  Client & Design Team & Project Director/Manager & CoW Client & Design Team & Project Director/Manager & CoW Client & Design Team & Project Director/Manager & CoW
Note change to role Attend meetings and give guidance  Attend meetings and give guidance  Attend meetings, give guidance and document review  Attend meetings, give guidance and document review  Review and give guidance
Type E         Construction Phase Plan Produce Safe Systems of work including  Health and Safety File Issued
  Tender Reviews Pre-Construction Information Method Statements, Permit to Works.
Initial Bid Review Gather Pre-Construction Information  Design Risk Register must mitigate any hazards and ensure controls are in place where there is a residual risk. Carry out Construction Site Inspection reports (Weekly/Monthly)
ITT and tender review Design Risk Register  Carry out reviews and alterations to the Construction Phase Plan when required *Only when there is a fundamental change to the scope of works
    Health and Safety file.

​ 

   Last updated 3 April 2023

​​

​​